HIGHER EDUCATION CLIENT LIST

State University at Geneseo

Geneseo, NY

  • Eric Sheffer was the Principal-in-Charge of electrical engineering for major mechanical, electrical and plumbing renovations to (3) dormitories on the SUNY Geneseo Campus.

  • The buildings each consisted of (3), three-story pods.  The renovations included power distribution and branch circuit replacements and additions, heating plant upgrades and toilet room renovations.  

State University at Binghamton 

Binghamton, NY

Academic Building Addition 

  • Programming phase for communications, technology and A/V systems for a new 70,000 square foot Academic Building to be located in downtown Binghamton.  

Dining Hall

  • Electrical design for expansion of main dining hall on SUNY Binghamton campus.  

Adirondack Community College

Gansevoort, NY

Electrical design for new four (4) story dormitory building, 2012 construction

Genesee Community College

Genesee, NY

Electrical design for site lighting and power distribution for new sports fields and courts. 

Purchase College

Purchase, NY

Electrical design for site lighting and power distribution for new sports fields and courts. 

NCAA/USTA Farmingdale State College

Farmingdale, NY

Electrical design for site lighting and power distribution for new sports fields and courts

University of Rochester 

Rochester, NY

Engineered Solutions has worked on multiple projects at the University of Rochester campus. 

ResNet and ResLife

  • ResNet and ResLife, which were structured cable plant for the University's Student Housing Division (19 Residence Halls).  Cable plant and PBX design for multiple off-site medical office locations.  

Hutchinson Hall

  • Designed modifications to the NMR and Mass Spectrometer Research Space, the Laminar Flow Hood Laboratory, the Monolayer Laboratory, the Confocal Microscope Room, the Plasma Mass Spectrometer Laboratory and the Laser Lab Room #220.  Master plan for Electrical and Plumbing upgrades

Laboratory for Laser Energetics

  • A 100,000-square-foot addition to the existing Laser Laboratory on the South Campus of the University of Rochester.  

State University at Albany

Albany, NY

  • Engineered Solutions performed electrical consulting for a comprehensive study with detailed options to build a new Data Center for the State University of New York at Albany.  Design criteria was to utilize existing warehouse space for the date center conversion.  The Study was completed in October 2008

  • Eric Sheffer was Principal-in Charge for the renovation to the University Theater.  

State University at Canton

Canton, NY

State University Construction Fund

  • Engineered Solutions performed design services for State University Construction Fund project included new network infrastructure for the campus.  The project included work in (18) buildings and was completed in 2011.

Payson Hall Renovations

  • MEP design for renovation of existing office and classroom areas, completed 2006.

St. John Fisher College

Rochester, NY

Kearney Hall Renovations

  • Project included campus-wide voice, data and video underground cabling and manhole system audit for the entire campus and satellite buildings (total 20)

Data Center Relocation

  • Data center relocation project included full MEP design, comprehensive backbone fiber system modifications for 500+ strands of fiber supporting LAN/WAN, DDC and fire alarm systems.  

engineered%20solutions_edited.png